FEATURED PROJECT
Soil Remediation & Underground Storage Tank Removal
GE Capital - Stamford, CT
RED was contracted by GE Capital in November 2008 to provide soil remediation and underground storage tank removal activities at this high-scale property. RED remediated, transported, and disposed of 20,000 tons of soil impacted with poly-aromatic hydrocarbons, coal, coal ash, arsenic and lead outside of the client’s fully-operational facility. Upon removal of impacted soils, RED worked to restore the landscape to original condition while maintaining a high level of safety and client satisfaction.
Key services performed by RED included:
► Earth Excavation
► Transportation and Disposal of Impacted Materials
► Trenching
► Drainage
► Electrical Work
► Paving